send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
Arun is 50% more efficient than Aman and Anil is 40% less efficient than Arun. The time taken by Anil alone to complete the work is 2 days more than the time taken by Aman alone to complete the work.
Quantity I: Find the time taken by Arun to complete 60% of the work with 60% of his original efficiency.
Quantity II: Find the time taken by Anil to complete 40% of the work with 80% of his original efficiency.
I =< II
Let the time taken by Aman to complete the work be x days. Time taken by Arun to complete the work = x/1.5 days Time taken by Anil to complete the work = (x/1.5)/0.6 = x/0.9 days Now, x/0.9 = x+2 => x = 18 days Time taken by Arun to complete the work = 18/1.5 = 12 days Time taken by Anil to complete the work = (x/1.5)/0.6 = 18/0.9 = 20 days From I: Time taken Arun to complete 60% of the work with 60% of his efficiency = 12/0.6*0.6 = 12 days From II: Time taken by Anil to complete 40% of the work with 80% of his efficiency = 20/0.8*0.4 = 10 days I > II
Hence, option 1 is the correct answer.