send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
Quantity 1: After working for 8 days .Anil finds that only 1/3 of the work has been done.He employs Rakesh who is 60% efficient as Anil.How many more days will Anil take to complete the job
Quantity 2: 8 men and 4 women together can complete a piece of work in 6 days. Work done by a man in one day is double the work done by a woman in one day. If 8 men and 4 women started working and after 2 days, 4 men left and 4 new women joined, in how many more days will the work be completed ?
Quantity 1 ≥ Quantity 2
Quantity 1 = Quantity 2 (or) No relation
Quantity 1 > Quantity 2
Quantity 1 ≤ Quantity 2
Quantity 1 < Quantity 2
Quantity 1:
In 8 days Anil does=1/3 rd work
In 1 day=1/24 thwork
Rakesh’s one day work=60% of 1/24=1/40 thwork
Remaining work=1-1/3=2/3
Anil & Rakesh’s one day’s work
=1/24+1/40=1/15 th
2/3 rd work=15×2/3=10 days
Quantity 2:
Work completed by 8M + 4W in 2 days = 2 ×1/6=1/3
Work done by 1 man = work done by 2 women
8 men + 4 women = (16 women + 4 women) = 20 women
8 men + 4 women = (8 men + 2 men) = 10 men
Work done by 20 women in 1 day = 1/20× 6 =1/120
Work done by 10 men in 1 day =1/10× 6 =1/60
As 4 men left and 4 new women joined, so 4M + 8W = 4 ×1/60+ 8 ×1/120=1/15+1/15=2/15
Work to be done = 1 -1/3=2/3
No of days required =(2/3)/(2/15)= 5 days.
Hence, option 3 is the correct answer.