send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
Direction : Read the following data and table to answer the following questions.
A construction company contractor has 5 workers Mr. A, Mr. B, Mr. C, Mr. D and Mr. E. Mr. A can do a work in 70 days. The table below shouls what time the other members will take to complete the same work with respect to the time taken by Mr. A. [Example +20 means 20 more days than Mr. A, -20 means , 20 days less than Mr. A ]. The table also shows the wage/day received by each worker.
Note: Even if a person has worked only for a fractional part of a day on which work got completed he will get full wage for that day. While a person will not get any wage for the day one which he does not works for a full day if the work is not completed on that day.
Total wage received by the most efficient person from the given data is how much greater than the wage received by the least efficient worker when they work together to complete the work?
Rs 7,000
Rs 7,500
Rs 9,300
Rs 8,100
None of these
Total wage of E = 36*300 =Rs 10,800 Total wage of C = 36*75 = Rs 2,700 Difference = Rs 8,100
hence, option 4 is the correct answer.