send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
20 men can complete a work in 14 days and 20 women can complete the same work in 18 days. 8 men start the work and after working for 21 days, they are replaced by x women. If the remaining work is to be completed by x women in 9 days, then how many women should be employed?
18
24
20
16
Explanation: 20M *14=20W*18 M/W=9/7 Total Work=20*9*14=2520 8 men work in 21 days=8*9*21=1512 remaining Work=2520-1512=1008 x *7*9=1008 x=16 women