send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
A, B and C can alone complete a work in 10, 12 and 15 days respectively. A and C started the work and after working for 4 days, A left and B joined. In how many days the total work was completed?
6( 5/9) days
6( 2/9 )days
6 days
5 (4/9) days
Answer & Explanation 6 2/9 days Explanation: (A+C) = (1/10 + 1/15) = 1/6. They worked for 4 days so did (1/6)*4 = 2/3rd of work Remaining work = 1 – 2/3 = 1/3 Now A left , B and C working (B+C) = (1/12 + 1/15) = 9/60 = 3/20. They worked for x days and completed 1/3rd of work so (3/20)*x = 1/3, so x = 20/9 days Total = 4 + 20/9
Report error
Tamanna Sharma
56/9
56/9=6(2/9)
answer is 52/9