send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
Ram decided to plough a farmland in 50 days. He employed 50 men in the beginning and 50 more after 35 days and completed the construction in stipulated time. If he had not employed the additional men, how many days behind schedule would it have been finished?
15 days
6 days
8 days
10 days
Explanation : Given that, 50 men employed for 35 days and 50 more men employed for 15 days so that the work could be finished in 50 days. Thus, the total work=50*35+(50+50)15=3250 Suppose, it takes x days to the finish the whole work, if additional men were not employed. So, we have an equation here. 50*x=3250 x=65 days Therefore, it takes 15 days more than stipulated time.