send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
A and B together can finish a task in 12 days. If A worked half as efficiently as he usually does and B works thrice as efficiently as he usually does, the task gets completed in 9 days. How long would A take to finish the task if he worked independently?
12 days
24 days
27 days
18 days
Let A take ‘a’ days to complete the task and B take ‘b’ days to complete the task. Thus in one day, A will complete (1/a)th of the task. Similarly in one day, B will complete (1/b)th of the task. So in one day, if A and B work together they will complete (1/a + 1/b)th of the task. Given that A and B together take 12 days to complete the task, then in one day A and B together complete (1/12)th of the task. Thus, 1/a + 1/b = 1/12 ……Eqn. 1 If A worked half as efficiently as he usually does, then A will take twice the time as he usually takes, i.e., 2a days. Thus in one day, A completes (1/2a)th of the task. Similarly if B worked thrice as efficiently as he usually does, then B will take one-third the time he usually takes, i.e., b/3 days. Thus in one day, B completed (1/(b/?/3))th or (3/b)th of the task. Thus when both of them work together, they will complete (1/2a + 3/b)th of the task, given that A and B take 9 days to complete the task. Thus, 1/a + 1/b = 1/12 ……Eqn. 1 1/2a + 3/b = 1/9 …… Eqn. 2 1/2a + 3/b = 1/9 …… Eqn. 2 Solving Equations 1 and 2 for ‘a’ we should get the answer, From equation (1) we get 12(a + b) = ab From equation (2), we get 9(b + 6a) = 2ab Substituting ab as 12(a + b) in equation (2) we get 9b + 54a = 2 x 12 x ( a + b) 9b + 54a = 24a + 24b; Or, 30a = 15b, Or, b = 2a Now, 12(a + b) = ab, or 12 x 3a = 2a2 a = 18 days.