send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
Kunal can do a piece of work in 60 days. He works at it for 10 days and then Mohit alone finishes the remaining work in 35 days. In how much time will Kunal and Mohit working together, finish the work?
258/13days
29days
200/13days
247/10days
Work done by kunal in 10 days = 1/60 ×10 = 1/6 Remaining work = (1 - 1/6) = 5/6 Now, 5/6 work is done by Mohit in 35 days. Whole work will be done by Mohit in (35×6/5) = 42days Kunal's 1 days work = 1/60 and Mohit's work = 1/42 (Kunal + Mohit)'s 1 days work = (1/60 + 1/42) = 17/420 days = 1/24.7 days = Hence both will finish the work in 247/10days