send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
21 men can do a piece of work in 25 days working 10 hours a day, then how many men are required to complete the work in 15 days by working 7 hours per day?
45 men
47 men
50 men
54 men
To solve this quesiton, we can apply the chain rule method M1 × D1 × H1 = M2 × D2 × H2 Given, M1 = 21 men, D1 = 25 days, H1 = 10 hours M2 = ?, D2 = 15 days, H2 = 7 hours M2 = M1 × D1 × H1 /D2 × H2 = 21 × 25 × 10 / 15 x 7 = 50 men