send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
A and B together can finish a piece of work in 10 days, B and C together do it in 12 days whereas A and C together finish it in 20 days. What is the respective ratio of the number of days taken by A when completing the same work alone to the number of days taken by C when completing the same work alone?
1 : 4
1 : 3
3 : 4
None of these
According to the question, 1/A + 1/B = 1/0 ..........i 1/B + 1/C = 1/12 ........II and 1/C + 1/A = 1/20 .....iii Adding eqn. (i), (ii) and (iii), we get 2(1/A + 1/B + 1/C) = 1/10 + 1/12 + 1/20 ⇒ 1/A + 1/B + 1/C = 7/60 ......iv Subtracting Eqn. (ii) from Eqn.(iv), we get 1/A = 7/60 - 1/12 = 2/60 = 1/30 Therefore, A will take 30 days to finish the whole work working alone. Now, Subtracting Eqn. (i) from Eqn.(iv), we get 1/C = 7/60 - 1/10 = 7 - 6/60 = 1/60 Therefore, C will take 60 days to finish the whole work working alone. ∴ Reqd ratio of days = 30 : 60 = 1 : 2
By: Amit Kumar ProfileResourcesReport error