send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
A, B and C working alone can complete a piece of work in 12, 15 and 20 days respectively.Each one does equal amount of work one by one. As soon as one’s part of work is done, the one can leave. In how many days will the work get finished?
11 2/3 days
13 2/3 days
15 2/3 days
9 2/3 days
Part of work done by each person = 1/3 Let A, B and C can complete 1/3rd of the work in x, y and z days respectively, Part of work done by A in one day = 1/12 Part of work done by B in one day = 1/15 Part of work done by C in one day = 1/20 According to the question, x/12 = 1/3 ⇒ x = 12/3 = 4 days y/15 = 1/3 ⇒ y = 15/3 = 5 days z/20 = 1/3 ⇒ z = 20/3 = 6 2/3 days Total number of days = 4 + 5 + 6 2/3 = 15 2/3 days
By: Amit Kumar ProfileResourcesReport error