send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
If Ajay completes a project in 7 days and Kajol alone completes the same project in 8 days, then in how many days will they complete the project if they both work together?
2.57
3.73
5.55
Ajay alone completes the project in 7 days ∴ Work completed by Ajay in one day = 1/7 Kajol alone completes the project in 8 days ∴ Work completed by Kajol in one day = 1/8 ∴ Work completed by Ajay and Kajol in one day = 1/7 + 1/8 = 15/56 Number of days to complete the work = 1/work done in one day = 56/15 = 3.73 days ∴ Ajay and Kajol working together can finish the work in 3.73 days.