send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
A can finish a work in 5 days and B takes 4 days to do the same work. If the work is increased by 8 times, How many days will it take for both of them to finish the work if they work together?
10 days
15 days
25 days
20 days
Let the total work be 100% A can do the work in 5 days, so he can do 20% work in 1 day B can do the work in 4 days, so he can do 25% work in 1 day Together they can do 20+25 = 45% work in 1 day Now the work is increased by 800%, so the work becomes 900% The work can be done in 900/45 = 20 days
By: Amit Kumar ProfileResourcesReport error