send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
To do a certain task Bhuvan would take 3 times as long as Abir and Varun together; and Varun would takes 4 times as long as Abir and Bhuvan together. Three of them together can complete the task in 5 days. How much time is taken by Bhuvan and varun to complete the task?
14 1/2 days
13 1/3 days
12 days
11 1/9 days
Let us represent efficiency of Abir, Bhuvan and Varun by A, B and V respectively. According to the question, B / A + V = 1/3 ........i V / A + B = 1/4 ........ii To equate the ratio in the above equations, let us multiply (1) by 5 and (2) by 4. So, A : B : V = 11 : 5 : 4 11 + 5 + 4 = 20 units In 5 days, task completed = 20 × 5 = 100 units (total task) Time taken by Bhuvan and Varun to complete the task = 100 /4 + 5 = 11 1/9 days
By: Amit Kumar ProfileResourcesReport error