send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
Salim taken 8 days to finish a piece of work. Manoj takes 12 days to finish the same piece of work. Raj works twice as fast as Salim. How many days will all three of them together take to finish the same piece of work?
2 3/11
3 8/13
5 2/3
2 2/11
If A, B and C can do a work in x, y and z days respectively then all of them working together can finish the work in (xyz /xy + yz + zx) days Given: Time taken by Salim = x = 8 days Time taken by Manoj = y = 12 days Time taken by Raj (Twice as fast as Salim) = z = 8/2 = 4 days By the short trick approach: A, B and C can do the work in = 8 × 12 × 4 /8×12 + 12×4 + 4×8 After taking 8 as a common term we get, = 48 /12 + 6 +4 = 48/22 = 24/11 = 2 2/11
By: Amit Kumar ProfileResourcesReport error