Multiple Choice Questions on Four person P Q R S were engaged for doing a task with the condition that P Q R S work respectively ........... for SSC (MTS) Preparation

Ratio, Proportion

Quantitative Aptitude (MTS)

Title

45:30

Video Progress

8 of 24 completed

Notes Progress

5 of 15 completed

MCQs Progress

38 of 100 completed

Subjective Progress

8 of 20 completed

Continue to Next Topic

Indian Economy - Understanding the basics of Indian economic system

Next Topic

    Four person P, Q, R, S were engaged for doing a task, with the condition that P; Q; R; S work respectively,on (Mondays,

    Thursdays); (Tuesdays, Fridays); (Wednesdays, Saturdays); (Sundays). The task was began on a Monday,and got completed on

    the 15th day, which was also a Monday.If the efficiencies of P, Q, R, S in respect of doing this task were in the proportion 1 : 2 :

    3 : 4,then in how many days could R completed the task,working alone without break?

    This questions was previously asked in
    SSC MTS 12th October 2021 Shift-2

    13

    Incorrect Answer

    10

    Incorrect Answer

    11

    Correct Answer

    12

    Incorrect Answer
    Explanation:

    - Day Sequence: The task starts on Monday and finishes on the 15th day, which is a Monday. Thus, two full weeks plus one day are included.

    - Workdays: Each person’s working days are scheduled as follows:

    - P: Mondays and Thursdays (4 days)

    - Q: Tuesdays and Fridays (4 days)

    - R: Wednesdays and Saturdays (4 days)

    - S: Only on Sundays (2 days)

    - Efficiency Proportion: P, Q, R, S work in ratio 1:2:3:4. So, if P completes 1 unit of work per day, R completes 3 units per day.

    - Calculating Total Work: Since the task takes 15 days to complete, we calculate the amount of work done by each:

    - Total work units done by P in 4 days = 4 units

    - Total work units done by Q in 4 days = 8 units

    - Total work units done by R in 4 days = 12 units

    - Total work units done by S in 2 days = 8 units

    - Overall work = 4 + 8 + 12 + 8 = 32 units

    - R’s Work: If R completes 3 units per day, to finish 32 units alone, it would take \( \frac{32}{3} \approx 10.67 \) or effectively around 11 days.

    - Correct Answer: Option:3, 11 days


    ProfileResources

    Download Abhipedia Android App

    Access to prime resources

    Downlod from playstore
    download android app download android app for free