16 boys or 12 women can do a piece of work in 28 days. In how many days will the same work be done by 4 boys and 4 women,
if they all work together?
This questions was previously asked in
SSC MTS 12th July 2022 Shift-2
Explanation:
- Start by calculating the work rate:
- 16 boys can complete the work in 28 days.
- Hence, 1 boy can complete the work in \(28 \times 16 = 448\) boy-days.
- Similarly, 12 women can complete the work in 28 days.
- Hence, 1 woman can complete the work in \(28 \times 12 = 336\) woman-days.
- Calculate the combined work rate:
- If 1 boy does \( \frac{1}{448} \) of work per day, then 4 boys do \( \frac{4}{448} = \frac{1}{112} \) of work per day.
- If 1 woman does \( \frac{1}{336} \) of work per day, then 4 women do \( \frac{4}{336} = \frac{1}{84} \) of work per day.
- Work done by 4 boys and 4 women together:
- Combined work rate = \( \frac{1}{112} + \frac{1}{84} = \frac{3}{336} + \frac{4}{336} = \frac{7}{336} = \frac{1}{48} \).
- Time taken for all to complete the work:
- Thus, they will complete the work in 48 days.
- Correct Answer:
- Option 2: 48 days
.