send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
A, B and C together can complete a work in 20 days. A and B together can complete the same work in 30 days. Then C alone can complete the same work in how many days?
10
30
45
60
Let’s break it down:
- A + B + C can finish the work in 20 days. So in 1 day, together, they do 1/20 of the work.
- A + B can do it in 30 days, so in 1 day, they get through 1/30 of it.
- If you subtract (A+B)’s 1-day work from (A+B+C)’s 1-day work, you get C's solo 1-day work: 1/20 - 1/30 = (3-2)/60 = 1/60.
- So, C alone will finish in 60 days.
Now, for the options:
1. 10 days – Way too quick, not realistic given the group speeds.
2. 30 days – Still too fast for just C alone, since A+B need 30.
3. 45 days – Closer, but C’s real pace is slower.
4. 60 days – That's the one that fits the math and logic.
So, Option 4 (60 days) is the accurate answer.