send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
A can do a piece of work in 12 days and B in 20 days. If they together work on it for 5 days, and remaining work is completed by C in 3 days, then in how many days can C do the same work alone?
10 days
9 days
12 days
15 days
- A completes the entire work in 12 days. So, A's one-day work is 1/12 of the work.
- B completes the entire work in 20 days. So, B's one-day work is 1/20 of the work.
- When A and B work together for 5 days, their combined one-day work is (1/12 + 1/20).
- Calculating the combined work:
$$
\frac{1}{12} + \frac{1}{20} = \frac{5 + 3}{60} = \frac{8}{60} = \frac{2}{15}
- In 5 days, they complete:
5 \times \frac{2}{15} = \frac{10}{15} = \frac{2}{3}
- So, 1/3 of the work remains.
- C completes this remaining 1/3 of work in 3 days.
- Therefore, 3 days is 1/3 of the time C would take to do the whole work alone.
- So, C can complete the work alone in:
3 \times 3 = 9 \text{ days}
- Option 2: 9 days is the correct answer.
By: Parvesh Mehta ProfileResourcesReport error