send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
A and B together can complete a work in 30 day. They started together but after 6 days A left the work and the work is completed by B after 36 more days. A alone can complete the entire work in how many days?
45
90
60
120
- A and B together do work in 30 days. So, they complete 1/30 of the work in a day.
- Together, they work 6 days. So, they finish 6/30 or 1/5 of the work in 6 days.
- B completes the remaining work alone in 36 days, which is 4/5 of the work.
- If B completes 4/5 of the work in 36 days, he completes 1/5 of the work in 9 days.
- So, B alone completes the entire work in 45 days (9 x 5 = 45).
- The work done by B in a day is 1/45.
- The combined work per day is 1/30. Therefore, A's work per day is 1/30 - 1/45 = 1/90.
- A alone can complete the entire work in 90 days.