send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
Which among the following risk is borne by the public sector partner ?
Financing risk
Construction risk
operation Maintenance risk
Termination risk
Some typical scenarios that may lead to the termination of a PPP contract are:
1.default events (this could be the insolvency of a party or its material breach of the contract) 2.the impossibility for the parties to perform under the contract (for example, due to a prolonged force majeure event) 3.government voluntary termination due to public policy.
Termination can be particularly expensive for governments once construction is complete and operations have commenced, where the full costs of construction have been born by the project company. Where compensation due from the procuring authority is based on the repayment of some level of debt, this will be highest immediately after construction before any debt drawn down for construction has been repaid.
Where a contract is terminated, possession of the public asset in question will often revert to the procuring authority. As a result, the procuring authority will be required to pay the private partner compensation agreed in the contract or prescribed by law, as the private partner will no longer have the project’s cash flows available to satisfy investors.