send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
A contractor appoints 100 men assuming he could complete a work in 40 days but after 35 days he appoints 100 more men and completes the work in a given time. If he had not appointed that 100 more men, how many days behind (extra) the schedule the work would have been completed?
50days
35days
40days
45days
200 × 5 = 100 × d d = 10 100men work 35 days and 200 men work 5 days Total 40 days Behind The Scheduled time -> 5 days total = 40 +5 = 45 days