Multiple Choice Questions on A contractor decided to complete a work in 90 days He employed 250 men at the beginning and another ........... for Mathematics - All Exams Preparation

Time and work

Quant (SSC)

Title

45:30

Video Progress

8 of 24 completed

Notes Progress

5 of 15 completed

MCQs Progress

38 of 100 completed

Subjective Progress

8 of 20 completed

Continue to Next Topic

Indian Economy - Understanding the basics of Indian economic system

Next Topic

    A contractor decided to complete a work in 90 days. He employed 250 men at the beginning and another 150 men after 60 days and completed the work in stipulated time. Had he not employed the additional men, what percent more time he would have taken to finish the work?

    27%

    Incorrect Answer

    30%

    Incorrect Answer

    20%

    Correct Answer

    50%

    Incorrect Answer
    Explanation:

    Let 250 men alone can complete the work in x days
    According to the question
    250 × 60 + (250 + 150) × (90 – 60) = 250 × x
    ⇒ 15000 + 12000 = 250 × x
    ⇒ x = 27000/250 = 108 days
    Reqd. percentage = 108 - 90 /90 x 100 = 20%