    If 5 men or 8 women can do a piece of work in 12 days, how many days will be taken by 2 men and 4 women to do the same work?

    15 days

    Incorrect Answer

    13 1/2 days

    Incorrect Answer

    8/3 days

    Correct Answer

    10 days

    Incorrect Answer
    Explanation:

    FOR MEN -

    3 men complete work in 16 days

    So 3 men one day work= 1/16

    1 men one day work = 1/16×3

    FOR WOMEN

    4 women complete work in 16 days

    So 4 women one day work= 1/16

    1 women one day work = 1/16×4

    Now we have to find when both (12 Men & 8 Women) are working together

    So 12 Men one day work = 12 × (one day work of one man)

    =12 × (1 / 16×13) =1/4

    So 8 Women one day work = 8 × (one day work of one woman)

    = 8 × (1 / 16×4) =1/8

    Adding one day of (12 Men) & (8 Women)

    = (1/4) + (1/8) = 3/8

    This means 12 Men and 8 Women does 3/8 fraction of work in one day

    Thus they would complete the work in 8/3 days.

    Hence, option 3 is the correct answer.